| Project Milestone | Description (Days from Appointed Date) | Planned | Actual | Remark | Current Status | ||
|---|---|---|---|---|---|---|---|
| Physical Progress (%) | Scheduled Date |
Date of completion | |||||
| Milestone I | 159 Days | 20% | 22/5/2019 | 24/06/2019 | with grace period | Achieved | |
| Milestone II | 358 Days | 35% | 7/12/2019 | 30.09.2019 | ahead scheduled date | Achieved | |
| Milestone III | 484 Days | 75% | 11/7/2020 | Achieved within the time frame | 6-months EOT on account of COVID-19 | Achieved | |
| Scheduled Completion | 730 Days | 100% | 13/03/2020 | 6-months EOT on account of COVID-19 | Provisional Completion issued on 31.03.2021. | ||